Note: If any work is accomplished the work program should implement all work consistent with the direction of the selected master plan.
Not listed nor estimated: repair and maintenance; landscape care; cleaning,
12.1.1 First Priority – Immediate Goals
If item of
work could produce income with a cash flow pay back of less than 2 year
period, or latent space expansion, or energy upgrade
Any
structure of life safety / Health Code related issue
Active leak
related to exterior membrane, ie. Roof or basement leak or plumbing leak
Any repair
item which will cause operation to stop or income to be reduced
12.1.2 Short Range Goals
A deferred
repair or upgrade which affects operation or appearance
Exterior
membrane maintenance program ie. Roof and tuck pointing
Remaining
life safety / health citations or "Grandfather" code issues Medium
range Goals
12.1.3 Space Medium Range Goals
When minor
repairs are deferred and expense increase as time lapses
Deferred
upgrade which can compound and will cause future cash problems ie.: if
sprinkler repair is not implemented in a phased basis; (the 1st Step:
of installing water service and Siamese to exterior 2nd Step: riser
the; 3rd Step: distribution / sprinkler heads)
12.1.4 Long Range Goals
Expansion /
Upgrade - Improvements which retain building integrity yet meets new
user needs and long range plan
Part I: Defers and Band Aids
12.2.1 Legend
Code
Description
EM
Exterior
Membrane/ roof gutter masonry
LS
Life
Safety
S
Structure
PM
Property
Maintenance
RM
Repair
and Maintenance
HC
Health
Code
A
Alarm
M
Mechanical
H
Heating
PL
Plumbing
E
Electrical/
lighting
CS
Civil/
site
UN
User
Needs
E
Energy
DoF
Date of
Failure
CD
Critical Date
12.2.2 Summary
Years
Date
Low - $/K
High - $/K
I
Immediate
=
0
Now-2003
$71
$118
SR
Short
Range
=
1-3
2004-2007
$227
$348
SR/MR
Medium
=
1-6
2008-2009
$40
$50
MR
Medium
Range
=
7-10
2010-2014
$97
$149
LR
Long
Range
=
11-16
2015-2020
$203
$230
F
Future
=
16
or more
2020-up
$637,900
$893,800
The attached listing does not include, expansion,
furniture, appliances, equipment, carpeting, interior painting unless
specifically noted
Kitchen: Walls, Floor, Ceiling Storage
cabinets, soffits, SP, AC
Pantry/Room 0: Walls, Floor, Ceiling Storage
cabinets, soffits/Convert to Multipurpose room or Computer room with
wireless/ Storage room and video surveillance racks; SP; AC
Laundry: Add
storage, Laundry shelving; SP; AC; Service bathroom and mop storage sink
Chapter
Room: SP;
AC; New archival storage; ritual closet upgrade
Dining Room: Restore and rebuild mortar at
walls, SP, AC, Electric and lighting, Switches 4 gang; Rebuild oak
veneer pair doors
TV Room: Convert
to Directors Apartment; SP; AC
Study Room
12, 13, 17: SP;
AC
Attic: Insulate
and build wall with fire door/rated drop stair; Upgrade structure for AC
Closets:
Rooms 5
to 13 and 15, 16: Repair base, walls, and ceilings
Room
1-17: Upgrade floors
All:
Storage System Shelving
Option
1 – Standard
Option
2 – Heavy duty and flexible
12.3.1.2 House
Security/Alarm System
Add upgrade to
existing: Basement and 1stfloor
Add motion sensors at 2ndfloor and 3rdfloor to existing
New internal
“Night shut down” at exterior doors, basement/1stfloor windows and add panel at director's unit
Add zoned alarm sensor
to Ricker Library and glass case
12.3.1.3 Key
System
Upgrade master key to 5
rooms
New entry doors at
study and computer room key system
12.3.1.4 Exterior
Rebuild wood shutter
– rebuild dado at corners
New historic entry
light service and replace facade illumination
New building address
and building letters
New National Register
Pier – 2 new plaques
Landscape Rear
new slopes, pea
gravel and rose plants (see drawing);
steps to replace RR
ties;
rebuild east brick
terrace with positive drainage;
plant Colorado
Spruce (8) and Arborvitae (see fence plan)