12 Budget

12.1 Goals and Priorities

Note: If any work is accomplished the work program should implement all work consistent with the direction of the selected master plan.

  1. Not listed nor estimated: repair and maintenance; landscape care; cleaning,

12.1.1 First Priority – Immediate Goals

  1. If item of work could produce income with a cash flow pay back of less than 2 year period, or latent space expansion, or energy upgrade

  2. Any structure of life safety / Health Code related issue

  3. Active leak related to exterior membrane, ie. Roof or basement leak or plumbing leak

  4. Any repair item which will cause operation to stop or income to be reduced

12.1.2 Short Range Goals

  1. A deferred repair or upgrade which affects operation or appearance

  2. Exterior membrane maintenance program ie. Roof and tuck pointing

  3. Remaining life safety / health citations or "Grandfather" code issues Medium range Goals

12.1.3 Space Medium Range Goals

  1. When minor repairs are deferred and expense increase as time lapses

  2. Deferred upgrade which can compound and will cause future cash problems ie.: if sprinkler repair is not implemented in a phased basis; (the 1st Step: of installing water service and Siamese to exterior 2nd Step: riser the; 3rd Step: distribution / sprinkler heads)

12.1.4 Long Range Goals

  1. Expansion / Upgrade - Improvements which retain building integrity yet meets new user needs and long range plan

Part I: Defers and Band Aids

12.2.1 Legend

Code

Description

EM

Exterior Membrane/ roof gutter masonry

LS

Life Safety

S

Structure

PM

Property Maintenance

RM

Repair and Maintenance

HC

Health Code

A

Alarm

M

Mechanical

H

Heating

PL

Plumbing

E

Electrical/ lighting

CS

Civil/ site

UN

User Needs

E

Energy

DoF

Date of Failure

CD

Critical Date

12.2.2 Summary


Years

Date

Low - $/K

High - $/K

 I 

 Immediate

=

 0

 Now-2003

$71 

$118 

 SR

 Short Range

=

 1-3

 2004-2007

$227 

$348 

 SR/MR

 Medium

=

 1-6

 2008-2009

$40 

$50 

 MR

 Medium Range

=

 7-10

 2010-2014

$97 

$149 

 LR

 Long Range

=

 11-16

 2015-2020

$203 

$230 

 F

 Future

=

 16 or more

 2020-up








$637,900 

$893,800 

The attached listing does not include, expansion, furniture, appliances, equipment, carpeting, interior painting unless specifically noted

*Note: Costs are based on 2003 cost estimates.

12.2.3 Budget

12.3  Part II: Wish List

12.3.1  Description

12.3.1.1  Possible Space Upgrades

  1. Kitchen: Walls, Floor, Ceiling Storage cabinets, soffits, SP, AC

  2. Pantry/Room 0: Walls, Floor, Ceiling Storage cabinets, soffits/Convert to Multipurpose room or Computer room with wireless/ Storage room and video surveillance racks; SP; AC

  3. Laundry: Add storage, Laundry shelving; SP; AC; Service bathroom and mop storage sink

  4. Chapter Room: SP; AC; New archival storage; ritual closet upgrade

  5. Dining Room: Restore and rebuild mortar at walls, SP, AC, Electric and lighting, Switches 4 gang; Rebuild oak veneer pair doors

  6. TV Room: Convert to Directors Apartment; SP; AC

  7. Study Room 12, 13, 17: SP; AC

  8. Attic: Insulate and build wall with fire door/rated drop stair; Upgrade structure for AC

  9. Closets:

    1. Rooms 5 to 13 and 15, 16: Repair base, walls, and ceilings

    2. Room 1-17: Upgrade floors

    3. All: Storage System Shelving

      1. Option 1 – Standard

      2. Option 2 – Heavy duty and flexible

12.3.1.2  House Security/Alarm System

  1. Add upgrade to existing: Basement and 1stfloor

  2. Add motion sensors at 2ndfloor and 3rdfloor to existing

  3. New internal “Night shut down” at exterior doors, basement/1stfloor windows and add panel at director's unit

  4. Add zoned alarm sensor to Ricker Library and glass case

12.3.1.3  Key System

  1. Upgrade master key to 5 rooms

  2. New entry doors at study and computer room key system

12.3.1.4  Exterior

  1. Rebuild wood shutter – rebuild dado at corners

  2. New historic entry light service and replace facade illumination

  3. New building address and building letters

  4. New National Register Pier – 2 new plaques

  5. Landscape Rear

    1. new slopes, pea gravel and rose plants (see drawing);

    2. steps to replace RR ties;

    3. rebuild east brick terrace with positive drainage;

    4. plant Colorado Spruce (8) and Arborvitae (see fence plan)

  6. Complete exterior security fence

  7. West Terrace
    1. Privet hedge expanded and upgrade

    2. Rebuild 3 limestone stairs & brick

    3. Raise terrace and upgrade drainage

    4. Crest Pedestal (see photo)

    5. Tree crab orchard and 2 bench seats

12.3.1.5  Equipment and Furniture

  1. Drapes/blinds at 1stand basement floors

  2. House computer, file cabinet, printer, telephones

  3. Library furniture and study lights

  4. Director's room furniture

  5. Study room furniture B,D,C x 34 each/Dorm Bunks

12.3.2  Budget

Last updated: 28-Jan-2007 by snachtigall